Engineer / Project Engineer, ConocoPhillips Indonesia, (various projects)

START Date: 
July, 2006
END Date: 
October, 2014

project engineer, development engineer for both onshore and offshore projects

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
50

Engineer / Project Engineer, Oman Power and Water Procurement Company, Barka IWP, Ibri IPP and Qurayyat IWP

START Date: 
January, 2018

- Monitor prject progress and HSE requirments

- Producing status reports to different level of management.

- Meeting with various stakeholders.

- Drafting emails, letters.

- HSE site inspections.

- Application of project managment knowledge areas.

- Status presentations and process improvements.

- witnessing acceptance test, monitoring observation list and calims managments.

Engineer / Project Engineer, PVC-MS, 10 beds Polybed PSA Unit Valve skid - Project: Dangote Refinery Project, Nigeria.

START Date: 
April, 2010
END Date: 
June, 2018

Project Engineer/ Planner

Experience Hours (Planning & Scheduling): 
900

Engineer / Project Engineer, PVC-MS, 10 beds Polybed PSA Unit Valve skid - Project: Dangote Refinery Project, Nigeria.

START Date: 
April, 2010
END Date: 
June, 2018

Project Engineer/ Planner

Experience Hours (Planning & Scheduling): 
900

Engineer / Project Engineer, PVC-MS, 10 beds Polybed PSA Unit Valve skid - Project: Dangote Refinery Project, Nigeria.

START Date: 
April, 2010
END Date: 
June, 2018

Project Engineer/ Planner

Experience Hours (Planning & Scheduling): 
900

Engineer / Project Engineer, PVC-MS, 10 beds Polybed PSA Unit Valve skid - Project: Dangote Refinery Project, Nigeria.

START Date: 
April, 2010
END Date: 
June, 2018

Project Engineer/ Planner

Experience Hours (Planning & Scheduling): 
900

Engineer / Project Engineer, PVC-MS, 10 beds Polybed PSA Unit Valve skid - Project: Dangote Refinery Project, Nigeria.

START Date: 
April, 2010
END Date: 
June, 2018

Project Engineer/ Planner

Experience Hours (Planning & Scheduling): 
900

Engineer / Project Engineer, Tornado Group, (2) 3B+G+14 Stories+ Swimming Pool (Office & Residential) Building

START Date: 
September, 2016

Manage project works inclding monitoring and controlling of scope, cost, time and quality.

Engineer / Project Engineer, Medad for Urban Development Co., Sahl Bin Al-Rabea Primary School

START Date: 
February, 2006
END Date: 
January, 2008
  • Preparing project programme using (Primavera V3.1).
  • Monitoring the execution of all works as per specifications.
  • Controlling the manpower, materials, equipment and the running of the site works as per schedule.
  • Site handing over.

Engineer / Project Engineer, Al Ghanim Trading, Services and Contracting Co., 7 Staff Housing Buildings

START Date: 
May, 2004
END Date: 
February, 2006
  • Monitoring the execution of all works as per specifications.
  • Controlling the manpower, materials, equipment and the running of the site works as per schedule.
  • Participating in the estimation of tenders.
  • Site handing over.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.