How to define Resource Productivity in Primavera P6 and create schedule

6 years 21 weeks ago

When create a schedule, we can based on Resource Productivity to estimate duration.

For example:

  • We have a team which can cast 10 m3 of concrete per day (This is Productivity)
  • We have an Foundation which take 100 m3 concrete.
  • Duration of Foundation activity will be  100 / 10 = 10 days

Now we will do it in Primavera.

Supposed

Read more...
 

Understanding the Planned Dates in Oracle Primavera P6

6 years 22 weeks ago

By Yaser A. Al-Bustanji CPCM, ACIArb, PMP, PMI-SP, PMI-RMP, November, 2017

Introduction

Of the many different types of date fields in Oracle® P6™, the most controversial and misleading dates are, "Planned Start" and "Planned Finish" dates of the activities.

There are several fields for start and finish dates in

Read more...
 

The Importance of the Product Owner and the Product Backlog

6 years 24 weeks ago

Agile is an effective software development framework.   Teams using Agile deliver value in short, iterative, increments.  The starting point of the delivery cycle is the Product Backlog.

The

Read more...
 

How to quickly identify Behind Schedule and Over Budget activity by Indicator UDF in Primavera P6

6 years 28 weeks ago

In Primavera P6, we can quickly identify behind schedule and over budget activity by using graphical indicator in User Defined Field.

I will show you how to do it.

Supposed that we have a project which has baseline. After update progress, we can show these column the see whether an activity is behind schedule:

  • BL Project Finish : Activity finish date from Project
Read more...
 

Effective Communications = Productive Project Teams

6 years 29 weeks ago

Effective communications are the cornerstone to successful projects and productive teams.   The Agile Manifestoextolls the virtues of collaboration, individual interactions, and face-to-face communications.  Projects represent our ability to coordinate the work of many people to accomplish a goal.  It is no surprise that project

Read more...
 

Driving Project Portfolio Risk & Opportunity Management for Benefit Realization

6 years 30 weeks ago

"Enhance opportunities and reduce threats by aligning sub-portfolios, programs and projects to meet organizational strategic goals"

This article illustrates the high-level components of Portfolio Risk & Opportunity Management. The risk is both threats and opportunity. The main goal is to minimize threats and maximize the opportunities for an organization.

Read more...
 

How to assign resource / resource loading / make resource plan in Primavera P6

6 years 33 weeks ago

In Primavera P6, after finish creating the schedule, you may need to assign resource to activity to make the resource plan.

I will show you how to do it.

Let say you have a schedule like in below picture:

Read more...
 

Stakeholder Management: A Key to Project Success

6 years 34 weeks ago

Projects with involved stakeholders are far more likely to be successful.  But many projects suffer from low engagement from executives, users, and key stakeholders.

The PMI’s Pulse of the Professionsurvey found that projects with high executive

Read more...
 

GAO is Wrong

6 years 34 weeks ago

GAO IS WRONG:

Activities have hundreds of fields and many might still be active if you only change a few.

Deleted_Activities_02

GAO Schedule Assessment Guide Best Practices for Project Schedules

Read more...
 

Why so many poor schedules?

6 years 37 weeks ago

Why so many poor schedules?

Schedule logic is not the issue, what makes our schedule models so poor is how we deal with resources. Without resources nothing is done.  Schedules that do not take into account all resource constraints are incomplete and most probably wrong.

We favor simplicity over substance and give the project manager very poor schedules he

Read more...
 

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.